This accounting problem is solved step by step below, with detailed explanations to help you understand the method and arrive at the correct answer.

ScanSolve AI Answer
Answer
Kshs 0.40 per direct labour hour
Hey, good to see you again.
The overhead application rate is calculated using the formula: Given budgeted figures: Budgeted Factory Overheads = Kshs 62,000 Budgeted Direct Labour Cost = Kshs 98,000 Budgeted Direct Labour Hours = 155,000 hours Budgeted Machine Hours = 50,000 hours
a) Direct labour hours Step 1: Identify the budgeted factory overheads and direct labour hours. Budgeted Factory Overheads = Kshs 62,000 Budgeted Direct Labour Hours = 155,000 hours Step 2: Calculate the overhead application rate. The overhead application rate on the basis of direct labour hours is:
b) Direct labour cost Step 1: Identify the budgeted factory overheads and direct labour cost. Budgeted Factory Overheads = Kshs 62,000 Budgeted Direct Labour Cost = Kshs 98,000 Step 2: Calculate the overhead application rate as a percentage of direct labour cost. The overhead application rate on the basis of direct labour cost is:
c) Machine hours Step 1: Identify the budgeted factory overheads and machine hours. Budgeted Factory Overheads = Kshs 62,000 Budgeted Machine Hours = 50,000 hours Step 2: Calculate the overhead application rate. The overhead application rate on the basis of machine hours is:
d) Overhead costs Step 1: Identify the budgeted factory overheads. Budgeted Factory Overheads = Kshs 62,000 Step 2: Calculate the overhead application rate based on overhead costs. This implies a rate per Kshs of overhead cost. The overhead application rate on the basis of overhead costs is:
e) Production cost Step 1: Determine the components of budgeted production cost. Budgeted Production Cost = Budgeted Direct Materials + Budgeted Direct Labour + Budgeted Factory Overheads. Step 2: Check for available budgeted figures. Budgeted Direct Labour = Kshs 98,000 Budgeted Factory Overheads = Kshs 62,000 Budgeted Direct Materials cost is not provided in the budget information. Only actual direct material costs are given. Step 3: Conclude on the calculation. Since the budgeted direct materials cost is not provided, the budgeted production cost cannot be determined, and therefore, the overhead application rate on the basis of production cost cannot be calculated.
Get instant step-by-step solutions to any question. Free to start.
Ask Your Question
Handwritten Step-by-Step Solution
Get this as a handwritten image on WhatsApp — like a tutor wrote it for you.
Try on WhatsAppStill have questions?
This accounting problem is solved step by step below, with detailed explanations to help you understand the method and arrive at the correct answer.