We read your photo as:
Calculate the overhead application rate using direct labour hours and direct labour cost as bases.
ScanSolve AI Answer
Step-by-step solution
11 stepsThe overhead application rate is calculated using the formula:
Given budgeted figures:
Budgeted Factory Overheads = Kshs 62,000
Budgeted Direct Labour Cost = Kshs 98,000
Budgeted Direct Labour Hours = 155,000 hours
Budgeted Machine Hours = 50,000 hours
Part a· 2 steps
Direct labour hours
Identify the budgeted factory overheads and direct labour hours.
Budgeted Factory Overheads = Kshs 62,000
Budgeted Direct Labour Hours = 155,000 hoursCalculate the overhead application rate.
The overhead application rate on the basis of direct labour hours is:
Part b· 2 steps
Direct labour cost
Identify the budgeted factory overheads and direct labour cost.
Budgeted Factory Overheads = Kshs 62,000
Budgeted Direct Labour Cost = Kshs 98,000Calculate the overhead application rate as a percentage of direct labour cost.
The overhead application rate on the basis of direct labour cost is:
Part c· 2 steps
Machine hours
Identify the budgeted factory overheads and machine hours.
Budgeted Factory Overheads = Kshs 62,000
Budgeted Machine Hours = 50,000 hoursCalculate the overhead application rate.
The overhead application rate on the basis of machine hours is:
Part d· 2 steps
Overhead costs
Identify the budgeted factory overheads.
Budgeted Factory Overheads = Kshs 62,000
Calculate the overhead application rate based on overhead costs.
This implies a rate per Kshs of overhead cost.
The overhead application rate on the basis of overhead costs is:
Part e· 3 steps
Production cost
Determine the components of budgeted production cost.
Budgeted Production Cost = Budgeted Direct Materials + Budgeted Direct Labour + Budgeted Factory Overheads.
Check for available budgeted figures.
Budgeted Direct Labour = Kshs 98,000
Budgeted Factory Overheads = Kshs 62,000
Budgeted Direct Materials cost is not provided in the budget information. Only actual direct material costs are given.Conclude on the calculation.
Since the budgeted direct materials cost is not provided, the budgeted production cost cannot be determined, and therefore, the overhead application rate on the basis of production cost cannot be calculated.
Still stuck on this one?
Ask a follow-up, and the answer starts from this question.
More Accounting Questions

Handwritten Step-by-Step Solution
Get this as a handwritten image on WhatsApp — like a tutor wrote it for you.
Try on WhatsApp