i)
SRTN (Shortest Remaining Time Next) Gantt Chart:

P1P2P4P1P3015101726\begin{array}{|c|c|c|c|c|} \hline P1 & P2 & P4 & P1 & P3 \\ \hline 0 & 1 & 5 & 10 & 17 & 26 \\ \hline \end{array}

Round Robin (RR) Gantt Chart (Time Slice = 4 milliseconds):

\begin{array}{|c|c|c|c|c|c|c|c|} \hline P1 & P2 & P3 & P4 & P