Five projects are competing for the same specialist employees. Senior managers currently approve projects based on who argues most persuasively. What is the strongest reason to introduce a project priority system?
ScanSolve AI Answer
Answer
To ensure projects are ranked consistently against strategic and resource criter
Step-by-step solution
5 stepsHere are the solutions to Questions 17 and 18:
Part 17· 2 steps
Five projects are competing for the same specialist employees. Senior managers currently approve projects based on who argues most persuasively. What is the strongest reason to introduce a project priority system?
Analyze the current problem.
The current method of approving projects is subjective ("who argues most persuasively") and leads to inconsistent decision-making, especially when resources are limited. A project priority system aims to bring objectivity and consistency to project selection.
Evaluate the given options.
- a. To eliminate all management judgement: This is incorrect. While a priority system reduces subjectivity, it typically guides management judgment rather than eliminating it entirely, as strategic decisions often still require human input.
- b. To ensure projects are ranked consistently against strategic and resource criteria: This is correct. A priority system provides a standardized framework with objective criteria (like strategic alignment and resource availability) to consistently evaluate and rank projects, addressing the problem of subjective approval.
Part c
To guarantee that the cheapest project is selected*: This is incorrect. A priority system aims to select projects that offer the most value or strategic fit, not necessarily just the cheapest ones.
- d. To allow departments to protect their own resources: This is incorrect. A priority system is for organizational-level resource allocation and project selection, often requiring departments to release resources for higher-priority projects, rather than protecting them.
The correct option is b. To ensure projects are ranked consistently against strategic and resource criteria.
Part 18· 3 steps
In a functional structure, a project manager repeatedly waits for departmental managers to release staff, causing delays. Which structural weakness is most evident?
Understand the characteristics of a functional structure in project management.
In a functional organizational structure, employees are grouped by their specialized functions (e.g., engineering, marketing). Project managers in such structures typically have limited authority and must negotiate with functional managers to acquire and utilize resources (staff). Functional managers prioritize their departmental goals.
Analyze the described problem.
The project manager "repeatedly waits for departmental managers to release staff, causing delays." This directly highlights a lack of authority for the project manager over project resources and a dependency on functional managers. This often leads to resource conflicts and delays because functional managers may prioritize their departmental work over project needs.
Identify the most evident structural weakness.
The most evident structural weakness is the lack of project manager authority and control over resources, leading to resource contention and delays. (The options for this question are not visible in the image, so a specific option cannot be selected).
Try one yourself
A new problem that tests the same skill.
Still stuck on this one?
Ask a follow-up, and the answer starts from this question.
More Business/Management Questions

Handwritten Step-by-Step Solution
Get this as a handwritten image on WhatsApp — like a tutor wrote it for you.
Try on WhatsApp