Here are the solutions to Questions 17 and 18:
Question 17: Five projects are competing for the same specialist employees. Senior managers currently approve projects based on who argues most persuasively. What is the strongest reason to introduce a project priority system?
Step 1: Analyze the current problem. The current method of approving projects is subjective ("who argues most persuasively") and leads to inconsistent decision-making, especially when resources are limited. A project priority system aims to bring objectivity and consistency to project selection.
Step 2: Evaluate the given options.
The correct option is b. To ensure projects are ranked consistently against strategic and resource criteria.
Question 18: In a functional structure, a project manager repeatedly waits for departmental managers to release staff, causing delays. Which structural weakness is most evident?
Step 1: Understand the characteristics of a functional structure in project management. In a functional organizational structure, employees are grouped by their specialized functions (e.g., engineering, marketing). Project managers in such structures typically have limited authority and must negotiate with functional managers to acquire and utilize resources (staff). Functional managers prioritize their departmental goals.
Step 2: Analyze the described problem. The project manager "repeatedly waits for departmental managers to release staff, causing delays." This directly highlights a lack of authority for the project manager over project resources and a dependency on functional managers. This often leads to resource conflicts and delays because functional managers may prioritize their departmental work over project needs.
Step 3: Identify the most evident structural weakness. The most evident structural weakness is the lack of project manager authority and control over resources, leading to resource contention and delays. (The options for this question are not visible in the image, so a specific option cannot be selected).
3 done, 2 left today. You're making progress.
Get instant step-by-step solutions to any question. Free to start.
Ask Your Question
Handwritten Step-by-Step Solution
Get this as a handwritten image on WhatsApp — like a tutor wrote it for you.
Try on WhatsAppStill have questions?
Question 17: Five projects are competing for the same specialist employees. Senior managers currently approve projects based on who argues most persuasively.
This business/management problem is solved step by step below, with detailed explanations to help you understand the method and arrive at the correct answer.