here are the solutions to Questions 18 and 19:
Question 18: In a functional structure, a project manager repeatedly waits for departmental managers to release staff, causing delays. Which structural weakness is most evident?
Step 1: Understand the nature of a functional structure in project management. In a functional organization, project managers have limited authority. Resources (staff) report directly to their functional managers, who control their assignments and priorities. Project managers must negotiate with functional managers to acquire staff for their projects.
Step 2: Analyze the problem described. The project manager "repeatedly waits for departmental managers to release staff, causing delays." This directly indicates that the project manager lacks direct control over resources and depends on the functional managers' willingness and availability to assign staff.
Step 3: Evaluate the given options.
The correct option is b. Weak access to resources and limited project ownership.
Question 19: In a matrix organisation, a project manager and functional manager share authority, but neither consistently has final control over project decisions. Which matrix form is most likely?
Step 1: Recall the characteristics of different matrix structures.
Step 2: Analyze the scenario. The scenario states that "a project manager and functional manager share authority, but neither consistently has final control over project decisions." This implies a situation where power is distributed, and decisions often require consensus or negotiation, rather than one party having ultimate authority.
Step 3: Match the scenario to the matrix forms. The description perfectly fits a balanced matrix structure, where the authority is shared, and the lack of a single, consistent decision-maker can be a characteristic challenge.
The correct option is b. Balanced matrix.
Drop the next question!
Get instant step-by-step solutions to any question. Free to start.
Ask Your Question
Handwritten Step-by-Step Solution
Get this as a handwritten image on WhatsApp — like a tutor wrote it for you.
Try on WhatsAppStill have questions?
Question 18: In a functional structure, a project manager repeatedly waits for departmental managers to release staff, causing delays.
This business/management problem is solved step by step below, with detailed explanations to help you understand the method and arrive at the correct answer.