Outline four aims of workstudy. Define motivation as a function of management. Highlight six factors to consider in determining the number of people in a span of control. State four benefits of delegation to each of the following in an organisation: supervisor; subordinates.

Business/Management

ScanSolve AI Answer

Step-by-step solution

7 steps

Huu hapa ni ufumbuzi wa maswali yako:

3. (a) Eleza malengo manne ya utafiti wa kazi (workstudy).

Malengo manne ya utafiti wa kazi ni:

  • Kuboresha mbinu za kazi: Kuchunguza na kurahisisha michakato ya kazi ili kuondoa hatua zisizo za lazima na kupunguza juhudi.
  • Kupima muda wa kazi: Kuamua muda wa kawaida unaohitajika kukamilisha kazi kwa kutumia mbinu bora.
  • Kuweka viwango vya utendaji: Kuanzisha viwango vya uzalishaji vinavyoweza kufikiwa na wafanyakazi.
  • Kuboresha mpangilio wa mahali pa kazi: Kuunda mazingira ya kazi yenye ufanisi zaidi kwa kupanga vifaa na rasilimali.

3. (b) Hesabu muda wa kawaida (standard time) kwa operesheni.

Tutatumia data kutoka Jedwali 2 na posho ya dharura ya 2%.

  1. Kokotoa muda halisi uliozingatiwa (Actual Observed Time, AOT) kwa kila kipengele katika kila mzunguko.

    Muda uliozingatiwa (OT) kwenye jedwali ni nyakati za jumla. Tunahitaji kupata muda halisi kwa kila kipengele.

    Mzunguko I:
    OTI,1=1.35 minOT_{I,1} = 1.35 \text{ min}
    OTI,2=2.65−1.35=1.30 minOT_{I,2} = 2.65 - 1.35 = 1.30 \text{ min}
    OTI,3=4.45−2.65=1.80 minOT_{I,3} = 4.45 - 2.65 = 1.80 \text{ min}
    OTI,4=6.75−4.45=2.30 minOT_{I,4} = 6.75 - 4.45 = 2.30 \text{ min}

    Mzunguko II:
    OTII,1=12.65−6.75=5.90 minOT_{II,1} = 12.65 - 6.75 = 5.90 \text{ min}
    OTII,2=13.85−12.65=1.20 minOT_{II,2} = 13.85 - 12.65 = 1.20 \text{ min}
    OTII,3=15.48−13.85=1.63 minOT_{II,3} = 15.48 - 13.85 = 1.63 \text{ min}
    OTII,4=17.95−15.48=2.47 minOT_{II,4} = 17.95 - 15.48 = 2.47 \text{ min}

    Mzunguko III:
    OTIII,1=26.45−17.95=8.50 minOT_{III,1} = 26.45 - 17.95 = 8.50 \text{ min}
    OTIII,2=27.95−26.45=1.50 minOT_{III,2} = 27.95 - 26.45 = 1.50 \text{ min}
    OTIII,3=32.95−27.95=5.00 minOT_{III,3} = 32.95 - 27.95 = 5.00 \text{ min}
    OTIII,4=34.60−32.95=1.65 minOT_{III,4} = 34.60 - 32.95 = 1.65 \text{ min}

  2. Kokotoa muda wa wastani uliozingatiwa (Average Observed Time, AOT) kwa kila kipengele.

    AOT1=1.35+5.90+8.503=15.753=5.25 minAOT_1 = \frac{1.35 + 5.90 + 8.50}{3} = \frac{15.75}{3} = 5.25 \text{ min} AOT2=1.30+1.20+1.503=4.003=1.3333 minAOT_2 = \frac{1.30 + 1.20 + 1.50}{3} = \frac{4.00}{3} = 1.3333 \text{ min} AOT3=1.80+1.63+5.003=8.433=2.81 minAOT_3 = \frac{1.80 + 1.63 + 5.00}{3} = \frac{8.43}{3} = 2.81 \text{ min} AOT4=2.30+2.47+1.653=6.423=2.14 minAOT_4 = \frac{2.30 + 2.47 + 1.65}{3} = \frac{6.42}{3} = 2.14 \text{ min}
  3. Kokotoa muda wa kawaida (Normal Time, NT) kwa kila kipengele.

    Tumia formula: NT=AOT×OR100NT = AOT \times \frac{OR}{100}

    NT1=5.25×95100=4.9875 minNT_1 = 5.25 \times \frac{95}{100} = 4.9875 \text{ min} NT2=1.3333×105100=1.4000 minNT_2 = 1.3333 \times \frac{105}{100} = 1.4000 \text{ min} NT3=2.81×100100=2.8100 minNT_3 = 2.81 \times \frac{100}{100} = 2.8100 \text{ min} NT4=2.14×90100=1.9260 minNT_4 = 2.14 \times \frac{90}{100} = 1.9260 \text{ min}
  4. Kokotoa jumla ya muda wa kawaida (Total Normal Time, TNT) kwa operesheni.

    TNT=NT1+NT2+NT3+NT4TNT = NT_1 + NT_2 + NT_3 + NT_4 TNT=4.9875+1.4000+2.8100+1.9260=11.1235 minTNT = 4.9875 + 1.4000 + 2.8100 + 1.9260 = 11.1235 \text{ min}
  5. Kokotoa jumla ya posho ya kupumzika (Total Relaxation Allowance, TRA) kwa dakika.

    RA1=4.9875×25100=1.2469 minRA_1 = 4.9875 \times \frac{25}{100} = 1.2469 \text{ min} RA2=1.4000×26100=0.3640 minRA_2 = 1.4000 \times \frac{26}{100} = 0.3640 \text{ min} RA3=2.8100×32100=0.8992 minRA_3 = 2.8100 \times \frac{32}{100} = 0.8992 \text{ min} RA4=1.9260×27100=0.5199 minRA_4 = 1.9260 \times \frac{27}{100} = 0.5199 \text{ min} TRA=1.2469+0.3640+0.8992+0.5199=3.0399 minTRA = 1.2469 + 0.3640 + 0.8992 + 0.5199 = 3.0399 \text{ min}
  6. Kokotoa muda ulioruhusiwa (Allowed Time, AT) kabla ya posho ya dharura.

    AT=TNT+TRAAT = TNT + TRA AT=11.1235+3.0399=14.1634 minAT = 11.1235 + 3.0399 = 14.1634 \text{ min}
  7. Tumia posho ya dharura (Contingency Allowance) na kokotoa muda wa kawaida (Standard Time, ST).

    Posho ya dharura ni 2%.

    ST=AT×(1+Posho ya Dharura100)ST = AT \times \left(1 + \frac{\text{Posho ya Dharura}}{100}\right) ST=14.1634×(1+2100)ST = 14.1634 \times \left(1 + \frac{2}{100}\right) ST=14.1634×1.02ST = 14.1634 \times 1.02 ST=14.446668 minST = 14.446668 \text{ min}

    Kuzungusha hadi sehemu mbili za desimali:

    ST≈14.45 minST \approx 14.45 \text{ min}

    Muda wa kawaida kwa operesheni ni:

    14.45 min\boxed{\text{14.45 min}}
Was this helpful?

Still stuck on this one?

Ask a follow-up, and the answer starts from this question.

Got a different question?Ask your own question
Handwritten step-by-step solution preview

Handwritten Step-by-Step Solution

Get this as a handwritten image on WhatsApp — like a tutor wrote it for you.