The net present values of a capital project are as follows: Discount rate % 10 16 NPV $ 6000 (3000). What is the internal rate of return for this project?

Business/Management

ScanSolve AI Answer

Answer

C 14%\text{C } 14\%

Step-by-step solution

3 steps

To find the Internal Rate of Return (IRR) using the given Net Present Values (NPVs) at different discount rates, we can use linear interpolation.

  1. Identify the given values.

    • Lower discount rate (LL) = 10%10\%
    • NPV at lower rate (NPVLNPV_L) = \6,000$
    • Higher discount rate (HH) = 16%16\%
    • NPV at higher rate (NPVHNPV_H) = -\3,000$ (The value in parentheses indicates a negative NPV).
  2. Apply the linear interpolation formula for IRR.

    The formula is:

    IRR=L+NPVLNPVL−NPVH(H−L)\text{IRR} = L + \frac{NPV_L}{NPV_L - NPV_H} (H - L)

    Substitute the values: IRR=0.10+$6,000$6,000−(−$3,000)(0.16−0.10)\text{IRR} = 0.10 + \frac{\$6,000}{\$6,000 - (-\$3,000)} (0.16 - 0.10) IRR=0.10+$6,000$6,000+$3,000(0.06)\text{IRR} = 0.10 + \frac{\$6,000}{\$6,000 + \$3,000} (0.06) IRR=0.10+$6,000$9,000(0.06)\text{IRR} = 0.10 + \frac{\$6,000}{\$9,000} (0.06)

    IRR=0.10+23(0.06)\text{IRR} = 0.10 + \frac{2}{3} (0.06) IRR=0.10+0.04\text{IRR} = 0.10 + 0.04 IRR=0.14\text{IRR} = 0.14
  3. Convert the IRR to a percentage.

    IRR=0.14×100%=14%\text{IRR} = 0.14 \times 100\% = 14\%

    The calculated Internal Rate of Return is 14%14\%, which corresponds to option C.

    The final answer is C 14%\text{C } 14\%.

Was this helpful?

Try one yourself

A new problem that tests the same skill.

Still stuck on this one?

Ask a follow-up, and the answer starts from this question.

Got a different question?Ask your own question