If 16 women and 24 men can complete a work in 18 days, how many days will 24 men take to complete the same work, given that each woman takes twice as long as a man to complete the work?
ScanSolve AI Answer
Answer
Step-by-step solution
4 stepsDetermine the relationship between the work rates of a man and a woman.
The problem states that each woman takes twice as long as a man to complete the work. This means a man works twice as fast as a woman.
Let be the work rate of one man (work per day) and be the work rate of one woman (work per day).
Therefore, the work rate of a woman is half the work rate of a man:Calculate the combined work rate of 16 women and 24 men in terms of men's work rate.
The combined work rate is . Substitute :
So, 16 women and 24 men together have a work rate equivalent to 32 men.
Calculate the total amount of work.
The group of 16 women and 24 men (equivalent to 32 men) completes the work in 18 days.
Total Work = (Equivalent men's work rate) (Time taken)Calculate the number of days 24 men will take to complete the same work.
Let be the number of days 24 men will take. The work rate of 24 men is .
Equate the total work from Step 3 and this expression:
Divide both sides by (assuming ):
Solve for :
Thus, 24 men will take 24 days to complete the work.
The number of days 24 men will take to complete the work is .
Try one yourself
A new problem that tests the same skill.
Still stuck on this one?
Ask a follow-up, and the answer starts from this question.
More Mathematics Questions

Handwritten Step-by-Step Solution
Get this as a handwritten image on WhatsApp — like a tutor wrote it for you.
Try on WhatsApp