Stage 1: Why should Ubunye run a formal supplier evaluation and selection process now, rather than continuing with its current purchasing process? · Installations are currently delayed/late due to components arriving late. · Components are failing, resulting in call-backs/replacements. This is question & answer Her response Unstructured purchasing approach Inconsistent lead times and quality 18% delays in installations 6% early battery failures Risk of losing customers Need structured evaluation process Out of 2