We read your photo as:
Calculate the material and labor variances for table production based on the provided standard and actual costs.
Accounting
ScanSolve AI Answer
Step-by-step solution
12 stepsHere are the calculations for the material and labor variances for table production.
Data Extraction:
Standard Cost per Table:
- Iroko: 12 kg @ N5.60/kg = N67.20
- Polish: 0.5 liter @ N6.00/liter = N3.00
- Labor: 16 hours @ N12.00/hour = N192.00
Actual Production and Costs (August 2006):
- Tables produced: 1,240 units
- Iroko: 900 kg purchased and used for N22,500
- Polish: 500 liters purchased and used for N2,000
- Labor: 10,400 hours worked for N72,500
1. Material Price Variance (MPV)
Formula:
- a) Iroko Material Price Variance
Calculate Actual Price (AP) for Iroko.
$$ \text{AP (Iroko)} = \frac{\text{Actual Cost}}{\text{Actual Quantity}} = \frac{\text{N}22,500}{900 \text{ kg}} = \text{N}25.00/\text{kg} $$Calculate Iroko Material Price Variance.
$$ \text{MPV (Iroko)} = (\text{N}5.60 - \text{N}25.00) \times 900 \text{ kg} = (-\text{N}19.40) \times 900 \text{ kg} = -\text{N}17,460 $$ The variance is adverse because the actual price was higher than the standard price. * **Iroko Material Price Variance: N17,460 Adverse**- b) Polish Material Price Variance
Calculate Actual Price (AP) for Polish.
$$ \text{AP (Polish)} = \frac{\text{Actual Cost}}{\text{Actual Quantity}} = \frac{\text{N}2,000}{500 \text{ liters}} = \text{N}4.00/\text{liter} $$Calculate Polish Material Price Variance.
$$ \text{MPV (Polish)} = (\text{N}6.00 - \text{N}4.00) \times 500 \text{ liters} = (\text{N}2.00) \times 500 \text{ liters} = \text{N}1,000 $$ The variance is favorable because the actual price was lower than the standard price. * **Polish Material Price Variance: N1,000 Favorable**
2. Material Usage Variance (MUV)
Formula:- a) Iroko Material Usage Variance
Calculate Standard Quantity (SQ) for actual production.
$$ \text{SQ (Iroko)} = 12 \text{ kg/table} \times 1,240 \text{ tables} = 14,880 \text{ kg} $$Calculate Iroko Material Usage Variance.
$$ \text{MUV (Iroko)} = (14,880 \text{ kg} - 900 \text{ kg}) \times \text{N}5.60/\text{kg} = (13,980 \text{ kg}) \times \text{N}5.60/\text{kg} = \text{N}78,288 $$ The variance is favorable because less material was used than the standard quantity for the actual production. * **Iroko Material Usage Variance: N78,288 Favorable**- b) Polish Material Usage Variance
Calculate Standard Quantity (SQ) for actual production.
$$ \text{SQ (Polish)} = 0.5 \text{ liter/table} \times 1,240 \text{ tables} = 620 \text{ liters} $$Calculate Polish Material Usage Variance.
$$ \text{MUV (Polish)} = (620 \text{ liters} - 500 \text{ liters}) \times \text{N}6.00/\text{liter} = (120 \text{ liters}) \times \text{N}6.00/\text{liter} = \text{N}720 $$ The variance is favorable because less material was used than the standard quantity for the actual production. * **Polish Material Usage Variance: N720 Favorable**
3. Labor Rate Variance (LRV)
Formula:Calculate Actual Rate (AR).
Calculate Labor Rate Variance.
The variance is favorable because the actual labor rate was lower than the standard rate.
- Labor Rate Variance: N52,300 Favorable
4. Labor Efficiency Variance (LEV)
Formula:Calculate Standard Hours (SH) for actual production.
Calculate Labor Efficiency Variance.
The variance is favorable because fewer hours were worked than the standard hours for the actual production.
- **Labor Efficiency Variance: N113,280
Was this helpful?
Still stuck on this one?
Ask a follow-up, and the answer starts from this question.
Got a different question?Ask your own question
More Accounting Questions
QDetermine the material usage variance.QD) Standard material = 2kg/unit at les/kg. Actual: 1000 units produced using 2,200kg but be 6/kg. i)…QCalculate the direct material cost.QCalculate total cost and cost per piece for glass and plates using conventional and ABC methods…QCalculate the 'Actual cost' for each ingredient by multiplying 'qty' by 'cost per'. Complete the…