Using the Quantity Surveyor's record given in Appendix 'A', prepare an interim valuation for payment certificate No. 4.

Accounting

ScanSolve AI Answer

Answer

Ksh 2,567,858.50\text{Ksh } 2,567,858.50

Step-by-step solution

6 steps

Huu hapa ni ukokotozi wa tathmini ya muda kwa cheti cha malipo Na. 4:

  1. Kokotoa thamani ya kazi iliyokamilika kwa kila shughuli.

    Hii inajumuisha kuzidisha "AMOUNT IN BQ" na asilimia iliyokamilika.

    • Excavation: 580,200.00×0.93=539,586.00580,200.00 \times 0.93 = 539,586.00
    • Foundation, walling and oversite concrete: 230,400.00×0.72=165,888.00230,400.00 \times 0.72 = 165,888.00
    • Walling: 580,200.00×0.44=255,288.00580,200.00 \times 0.44 = 255,288.00
    • Openings: 130,600.00×0.25=32,650.00130,600.00 \times 0.25 = 32,650.00
    • Roofing: 720,000.00×0.51=367,200.00720,000.00 \times 0.51 = 367,200.00
    • Finishes: 920,550.00×0.12=110,466.00920,550.00 \times 0.12 = 110,466.00
    • Fillings: 380,900.00×0.09=34,281.00380,900.00 \times 0.09 = 34,281.00
    • Drainage: 1,893,420.00×0.35=662,697.001,893,420.00 \times 0.35 = 662,697.00
    • Plumbing: 2,344,205.00×0.60=1,406,523.002,344,205.00 \times 0.60 = 1,406,523.00
    • Electrical: 1,204,215.00×0.15=180,632.251,204,215.00 \times 0.15 = 180,632.25
    • External works: 2,004,230.00×0.40=801,692.002,004,230.00 \times 0.40 = 801,692.00
    • Preliminaries: 1,345,000.00×0.68=914,600.001,345,000.00 \times 0.68 = 914,600.00
  2. Jumlisha thamani ya kazi zote zilizokamilika.

    Jumla ya Kazi Iliyokamilika=539,586.00+165,888.00+255,288.00+32,650.00+367,200.00+110,466.00+34,281.00+662,697.00+1,406,523.00+180,632.25+801,692.00+914,600.00=5,471,503.25\text{Jumla ya Kazi Iliyokamilika} = 539,586.00 + 165,888.00 + 255,288.00 + 32,650.00 + 367,200.00 + 110,466.00 + 34,281.00 + 662,697.00 + 1,406,523.00 + 180,632.25 + 801,692.00 + 914,600.00 = 5,471,503.25
  3. Jumlisha thamani ya vifaa vilivyopo mahali.

    Jumla ya Vifaa Vilivyopo Mahali=25,000.00+28,000.00+32,000.00+48,000.00+28,000.00+110,000.00+52,000.00+24,000.00+45,000.00+15,000.00=407,000.00\text{Jumla ya Vifaa Vilivyopo Mahali} = 25,000.00 + 28,000.00 + 32,000.00 + 48,000.00 + 28,000.00 + 110,000.00 + 52,000.00 + 24,000.00 + 45,000.00 + 15,000.00 = 407,000.00
  4. Kokotoa jumla ya tathmini halisi.

    Hii ni jumla ya kazi iliyokamilika na vifaa vilivyopo mahali.

    Jumla ya Tathmini Halisi=5,471,503.25+407,000.00=5,878,503.25\text{Jumla ya Tathmini Halisi} = 5,471,503.25 + 407,000.00 = 5,878,503.25
  5. Jumlisha malipo yote ya awali.

    Jumla ya Malipo ya Awali=1,421,428.00+346,213.50+1,543,003.25=3,310,644.75\text{Jumla ya Malipo ya Awali} = 1,421,428.00 + 346,213.50 + 1,543,003.25 = 3,310,644.75
  6. Kokotoa kiasi kinachostahili kwa Cheti cha Malipo Na.

    Kiasi kinachostahili ni jumla ya tathmini halisi ukiondoa malipo ya awali.

    Kiasi Kinachostahili=5,878,503.25−3,310,644.75=2,567,858.50\text{Kiasi Kinachostahili} = 5,878,503.25 - 3,310,644.75 = 2,567,858.50

    Kiasi kinachostahili kwa Cheti cha Malipo Na. 4 ni:

    Ksh 2,567,858.50\text{Ksh } 2,567,858.50
Was this helpful?

Try one yourself

A new problem that tests the same skill.

Still stuck on this one?

Ask a follow-up, and the answer starts from this question.

Got a different question?Ask your own question
Handwritten step-by-step solution preview

Handwritten Step-by-Step Solution

Get this as a handwritten image on WhatsApp — like a tutor wrote it for you.

Try on WhatsApp