Draw an arrow diagram for the following project activities and their dependencies: A(2), B(1), C(3) depends on A, D(4) depends on B, E(2) depends on C and D.
Business/Management
ScanSolve AI Answer
a) Draw an arrow diagram for this project
To draw the arrow diagram (Activity-On-Arrow network), we represent activities as arrows and events (start/completion of activities) as nodes. Dummy activities (dashed arrows with 0 duration) are used to maintain correct precedence relationships without representing actual work.
Here's the step-by-step construction:
- Activities A and B have no predecessors, so they start from the initial node (Node 1).
- Node 1 Node 2
- Node 1 Node 3
- Activity C depends on A.
- Node 2 $\xrightarrow{\text{C
Was this helpful?
Still stuck on this one?
Ask a follow-up, and the answer starts from this question.
Got a different question?Ask your own question
More Business/Management Questions
QOn the diagram, label the parts A to D. 1. (c) (ii) State what happens at A, B and C.QDraw the network diagram for the project? (note that in constructing, dummy activity may be…QDetermine the operations for A, B, and C.Q& (ii) The activity list and their durations are required to draw the network diagram and determine…QDetermine the operations represented by A, B, and C.

Handwritten Step-by-Step Solution
Get this as a handwritten image on WhatsApp — like a tutor wrote it for you.
Try on WhatsApp