Draw an arrow diagram for the following project activities and their dependencies: A(2), B(1), C(3) depends on A, D(4) depends on B, E(2) depends on C and D.

Business/Management

ScanSolve AI Answer

a) Draw an arrow diagram for this project

To draw the arrow diagram (Activity-On-Arrow network), we represent activities as arrows and events (start/completion of activities) as nodes. Dummy activities (dashed arrows with 0 duration) are used to maintain correct precedence relationships without representing actual work.

Here's the step-by-step construction:

  1. Activities A and B have no predecessors, so they start from the initial node (Node 1).
    • Node 1 →A (2)\xrightarrow{\text{A (2)}} Node 2
    • Node 1 →B (1)\xrightarrow{\text{B (1)}} Node 3
  2. Activity C depends on A.
    • Node 2 $\xrightarrow{\text{C
Was this helpful?

Still stuck on this one?

Ask a follow-up, and the answer starts from this question.

Got a different question?Ask your own question
Handwritten step-by-step solution preview

Handwritten Step-by-Step Solution

Get this as a handwritten image on WhatsApp — like a tutor wrote it for you.

Try on WhatsApp