This law problem is solved step by step below, with detailed explanations to help you understand the method and arrive at the correct answer.

ScanSolve AI Answer
Answer
b. 36 inches, 36 inches
According to 49 CFR 195.248(c), when a pipeline is installed in a drainage ditch or at a public road or railroad crossing, the minimum cover is 48 inches for normal excavation and 36 inches for rock excavation.
However, 48 inches is not available as an option for normal excavation. Among the given choices, option b provides 36 inches for rock excavation, which is correct for this specific scenario. The 36 inches for normal excavation in option b corresponds to the general minimum cover requirement for normal excavation as per 49 CFR 195.248(a). Given the options, option b is the most appropriate choice.
The final answer is
Send me the next one 📸
Get instant step-by-step solutions to any question. Free to start.
Ask Your Question
Handwritten Step-by-Step Solution
Get this as a handwritten image on WhatsApp — like a tutor wrote it for you.
Try on WhatsAppStill have questions?
According to 49 CFR 195.248(c), when a pipeline is installed in a drainage ditch or at a public road or railroad crossing, the minimum cover is 48 inches for normal excavation and 36 inches for rock excavation.
This law problem is solved step by step below, with detailed explanations to help you understand the method and arrive at the correct answer.