Required: Contract A/C, Outer Cities Grabbers Ltd. (Contractee), Architects' Certificates A/C, and Retentions A/C

Accounting

ScanSolve AI Answer

Answer

000=450,000000 = 450,000

212,903.23

903.23=237,096.77903.23 = 237,096.77

Step-by-step solution

5 steps

Here are the required accounts for Example 2:

1. Contract A/C

Particulars£Particulars£To Plant150,000By Plant c/d100,000To Wages, etc.260,000By Materials c/d50,000To Materials330,000By Work-in-Progress c/d:To Sub-contract work200,000Work Certified1,550,000To Sundry Expenses30,000Work Uncertified20,000To Contract overheads240,000To Accrued wages60,000To Notional Profit c/d450,000Total1,720,000Total1,720,000To Notional Profit b/d450,000By Profit & Loss A/C212,903.23By Reserve for WIP237,096.77Total450,000Total450,000\begin{array}{|l|r|l|r|} \hline \textbf{Particulars} & \textbf{£} & \textbf{Particulars} & \textbf{£} \\ \hline \text{To Plant} & 150,000 & \text{By Plant c/d} & 100,000 \\ \text{To Wages, etc.} & 260,000 & \text{By Materials c/d} & 50,000 \\ \text{To Materials} & 330,000 & \text{By Work-in-Progress c/d:} & \\ \text{To Sub-contract work} & 200,000 & \quad \text{Work Certified} & 1,550,000 \\ \text{To Sundry Expenses} & 30,000 & \quad \text{Work Uncertified} & 20,000 \\ \text{To Contract overheads} & 240,000 & & \\ \text{To Accrued wages} & 60,000 & & \\ \text{To Notional Profit c/d} & 450,000 & & \\ \hline \textbf{Total} & \textbf{1,720,000} & \textbf{Total} & \textbf{1,720,000} \\ \hline \text{To Notional Profit b/d} & 450,000 & \text{By Profit \& Loss A/C} & 212,903.23 \\ & & \text{By Reserve for WIP} & 237,096.77 \\ \hline \textbf{Total} & \textbf{450,000} & \textbf{Total} & \textbf{450,000} \\ \hline \end{array}
  1. Calculate Total Debits and Credits for Notional Profit.

    • Total Debits = Plant + Wages + Materials + Sub-contract work + Sundry Expenses + Contract overheads + Accrued wages =150,000+260,000+330,000+200,000+30,000+240,000+60,000=1,270,000= 150,000 + 260,000 + 330,000 + 200,000 + 30,000 + 240,000 + 60,000 = 1,270,000
    • Total Credits = Plant c/d + Materials c/d + Work Certified + Work Uncertified =100,000+50,000+1,550,000+20,000=1,720,000= 100,000 + 50,000 + 1,550,000 + 20,000 = 1,720,000
    • Notional Profit = Total Credits - Total Debits =1,720,000−1,270,000=450,000= 1,720,000 - 1,270,000 = \boxed{450,000}
  2. Allocate Notional Profit to Profit & Loss A/C and Reserve for WIP.

    • Cash Received = Progress payments during 2019 = £1,100,000
    • Work Certified = £1,550,000
    • Profit to P&L = Notional Profit ×(Cash ReceivedWork Certified)×23\times \left(\frac{\text{Cash Received}}{\text{Work Certified}}\right) \times \frac{2}{3} (assuming 50-90% completion) =450,000×(1,100,0001,550,000)×23=450,000×0.709677419×0.666666667≈212,903.23= 450,000 \times \left(\frac{1,100,000}{1,550,000}\right) \times \frac{2}{3} = 450,000 \times 0.709677419 \times 0.666666667 \approx \boxed{212,903.23}
    • Reserve for WIP = Notional Profit - Profit to P&L =450,000−212,903.23=237,096.77= 450,000 - 212,903.23 = \boxed{237,096.77}

    2. Outer Cities Grabbers Ltd. (Contractee) A/C

    Particulars£Particulars£To Architects’ Certificates A/C1,550,000By Bank1,100,000By Retentions A/C150,000By Balance c/d300,000Total1,550,000Total1,550,000\begin{array}{|l|r|l|r|} \hline \textbf{Particulars} & \textbf{£} & \textbf{Particulars} & \textbf{£} \\ \hline \text{To Architects' Certificates A/C} & 1,550,000 & \text{By Bank} & 1,100,000 \\ & & \text{By Retentions A/C} & 150,000 \\ & & \text{By Balance c/d} & 300,000 \\ \hline \textbf{Total} & \textbf{1,550,000} & \textbf{Total} & \textbf{1,550,000} \\ \hline \end{array}
  3. Record transactions in Contractee A/C.

    • Debit the account with the value of work certified: £1,550,000.
    • Credit the account with progress payments received: £1,100,000.
    • Credit the account with retentions withheld: £150,000.
    • Credit the account with the balance receivable: £300,000. 1,100,000+150,000+300,000=1,550,0001,100,000 + 150,000 + 300,000 = 1,550,000 The account balances.

    3. Architects' Certificates A/C

    Particulars£Particulars£To Outer Cities Grabbers Ltd. A/C1,550,000By Contract A/C1,550,000Total1,550,000Total1,550,000\begin{array}{|l|r|l|r|} \hline \textbf{Particulars} & \textbf{£} & \textbf{Particulars} & \textbf{£} \\ \hline \text{To Outer Cities Grabbers Ltd. A/C} & 1,550,000 & \text{By Contract A/C} & 1,550,000 \\ \hline \textbf{Total} & \textbf{1,550,000} & \textbf{Total} & \textbf{1,550,000} \\ \hline \end{array}
  4. Record transactions in Architects' Certificates A/C.

    • Debit the account with the value of work certified from the Contractee A/C: £1,550,000.
    • Credit the account with the value of work certified from the Contract A/C: £1,550,000. The account balances.

    4. Retentions A/C

    Particulars£Particulars£To Outer Cities Grabbers Ltd. A/C150,000By Balance c/d150,000Total150,000Total150,000\begin{array}{|l|r|l|r|} \hline \textbf{Particulars} & \textbf{£} & \textbf{Particulars} & \textbf{£} \\ \hline \text{To Outer Cities Grabbers Ltd. A/C} & 150,000 & \text{By Balance c/d} & 150,000 \\ \hline \textbf{Total} & \textbf{150,000} & \textbf{Total} & \textbf{150,000} \\ \hline \end{array}
  5. Record transactions in Retentions A/C.

    • Debit the account with the retention amount from the Contractee A/C: £150,000.
    • Credit the account with the closing balance of retentions: £150,000. The account balances.
Was this helpful?