We read your photo as:
Calculate the Early Start, Early Finish, Late Start, Late Finish, and Slack for each activity, and draw a network diagram.
ScanSolve AI Answer
Answer
Step-by-step solution
3 stepsHere are the calculations for the project activities:
Part i· 3 steps
The Early Start, Early Finish, Late Start, Late Finish and the slack for all the activities
Perform a forward pass to calculate Early Start (ES) and Early Finish (EF) for each activity.
Perform a backward pass to calculate Late Finish (LF) and Late Start (LS) for each activity.
The project completion time is the maximum EF of all final activities.
Calculate Slack (Total Float) for each activity.
The calculated values are as follows:
Activity Duration Predecessor ES EF LS LF Slack A 2 - 0 2 0 2 0 B 5 A 2 7 17 22 15 C 8 A 2 10 5 13 3 D 6 A 2 8 2 8 0 E 8 A 2 10 16 24 14 F 9 B 7 16 23 32 7 G 10 B 7 17 22 32 5 H 8 C 10 18 24 32 6 I 17 C 10 27 13 30 3 J 22 D 8 30 8 30 0 K 6 E 10 16 24 30 8 L 8 F, G, H 18 26 32 40 6 M 10 I, J, K 30 40 30 40 0 N 12 L, M 40 52 40 52 0
Part ii
Draw a network and determine the Critical Path
A network diagram (Activity-On-Node) shows activities as nodes and precedence relationships as arrows. Due to the text-based format, a visual diagram cannot be drawn here. However, the critical path can be determined from the activities with zero slack.
The critical path is the longest path through the network, representing the minimum time required to complete the project. Activities on the critical path have zero slack.
The activities with zero slack are A, D, J, M, N.
The Critical Path is:
The project completion time is 52 units.
Part iii
Estimate the project schedules with the Gantt Chart
A Gantt chart visually represents the project schedule, showing the start and end times for each activity. Critical activities are typically highlighted. Below is the data required to construct the Gantt chart, using the Early Start (ES) and Early Finish (EF) times.
| Activity | Duration | ES | EF | Critical Path |
|---|---|---|---|---|
| A | 2 | 0 | 2 | Yes |
| B | 5 | 2 | 7 | No |
| C | 8 | 2 | 10 | No |
| D | 6 | 2 | 8 | Yes |
| E | 8 | 2 | 10 | No |
| F | 9 | 7 | 16 | No |
| G | 10 | 7 | 17 | No |
| H | 8 | 10 | 18 | No |
| I | 17 | 10 | 27 | No |
| J | 22 | 8 | 30 | Yes |
| K | 6 | 10 | 16 | No |
| L | 8 | 18 | 26 | No |
Try one yourself
A new problem that tests the same skill.
Still stuck on this one?
Ask a follow-up, and the answer starts from this question.
More Business/Management Questions

Handwritten Step-by-Step Solution
Get this as a handwritten image on WhatsApp — like a tutor wrote it for you.
Try on WhatsApp