How many people will be needed to erect the fence in 4 days? 2.2. If one person rates R70/hour. How much will be the total cost of labourers in 3 days if 3 people work for 8 hours a day?

ScanSolve AI Answer
Answer
28 people
Here are the solutions for Activity 2.
2.1
Step 1: Determine the total work units. The work required to erect the fence is constant. It is calculated as the number of people multiplied by the number of days.
Step 2: Calculate the number of people needed for the new timeframe. To complete the same amount of work in 4 days, we divide the total work by the new number of days.
To erect the fence in 4 days, 28 people will be needed.
2.2
Step 1: Calculate the total hours worked by one person. One person works for 8 hours a day for 3 days.
Step 2: Calculate the total hours worked by all labourers. There are 3 people working.
Step 3: Calculate the total cost. Each person rates R70 per hour.
The total cost of labourers will be R5040.
That's 2 down. 3 left today — send the next one.
Need help with your own homework?
Get instant step-by-step solutions to any question. Free to start.
Ask Your Question
Handwritten Step-by-Step Solution
Get this as a handwritten image on WhatsApp — like a tutor wrote it for you.
Try on WhatsAppMore Mathematics Questions
Still have questions?
Determine the total work units. The work required to erect the fence is constant.